Crystal Island Project 2-Week Look Ahead

June 22 – July 10, 2020

All of Crystal Island

• Slow Down In Work Zones!
• No parking on streets project-wide
• Keep children away from work areas

John’s Pass Ave. June 22-26

• Storm System - John's Pass - 546/549 to 568/571
• Finish Base - 538/541 to south cul-de-sac
• 6" WM Install Extend North - 577 to north cul-de-sac

Lillian Drive June 22-26

• Sub-Base and Base - 566/567 to Flamingo Dr
• Wet-Taps for Fire Hydrant Install
• Storm System - North end Tear Drop Park - Both Sides

Flamingo Drive June 22-26

• Seawall Southwest - Flamingo Dr (Between Crystal & Lillian)
• Box Culvert Tie-In - 6x3 to Seawall
• Traffic Switch - One Lane Flamingo Dr for 7x4 Box Culvert Install (6/25)

Crystal Drive June 22-26

• Wet-Taps for Fire Hydrant Install

John’s Pass Ave. June 29 – July 2

• Clean & TV Storm System
• Prime Finished Base - 538/541 to south cul-de-sac
• Prime Finished Base - 538/541 to south cul-de-sac

Lillian Drive June 29 – July 2

• Storm System - North end Tear Drop Park - Both Sides
• Sub-Base and Base North end of Tear Drop Park

Flamingo Drive June 29 – July 2

• Seawall Southeast - Flamingo Dr (Between Lillian & Johns Pass) - Finish Seawall cap
• Seawall Southwest - Flamingo Dr (Between Crystal & Lillian)
• Box Culvert Install - 7x4

Crystal Drive June 29 – July 2

• No work scheduled

Miscellaneous Project Wide

• Survey/Layout
• Quality Control Testing