Crystal Island Project : 2-Week Look Ahead

**SCHEDULED WATER SHUT OFF**
9am-3pm on Monday, 11/23.
Expected it to effect all residents on:
- Crystal Dr.
- Flamingo Ave.
- Lillian Dr.
- Johns Pass Ave.

 

Slow Down In Work Zones!
No parking on streets project-wide
Keep children away from work areas

Crystal Island Roadway / Drainage Schedule

Monday November 16th – Friday November 20th

Lillian Dr.

  • Irrigation Restoration
  • Copper water service lines replaced

Johns Pass Ave.

  • Irrigation Restoration
  • Restore Driveways

Flamingo Dr.

  • Restore Driveways
  • Reclaim water offset
  • Pump Station Valve Replacement

Crystal Dr.

  • Sub-Base and Base South of Flamingo Drive - Existing Base
  • Prep for curb pad
  • Machine Curb Install - 528/529 up to Flamingo Drive
  • Reclaim water offset
  • Watermain offset

Outfall Storm Pipes Install - Drainage Easements

  • Storm Outfall Pipe - 498 Crystal Drive
  • Storm Outfall Pipe - 496/498 John's Pass
  • Storm Outfall Pipe - 537/539 Lillian Dr

Misc. Project wide

  • Quality Control testing

Monday November 23rd & Tuesday November 24th

No work scheduled Wednesday November 25th – Friday November 27th

Lillian Dr.

  • Irrigation Restoration

Johns Pass Ave.

  • Irrigation Restoration
  • Restore Driveways

Flamingo Dr.

  • Restore Driveways

Crystal Dr.

  • Sub-Base and Base South of Flamingo Drive - Existing Base
  • Prep for curb pad
  • Water Main Offset work for Storm Conflict
  • Machine Curb Install SB lane (extent of work will be listed on door hangers).
  • Replace Driveways - Concrete

Outfall Storm Pipes Install - Drainage Easements

  • Storm Outfall Pipe - 498 Crystal Drive
  • Storm Outfall Pipe - 496/498 John's Pass
  • Storm Outfall Pipe - 537/539 Lillian Dr

Misc. Project wide

  • Quality Control testing