Crystal Island Project : 2-Week Look Ahead
Slow Down In Work Zones!
No parking on streets project-wide
Keep children away from work areas
Crystal Island Roadway / Drainage Schedule
Monday December 21st - Wednesday December 23rd
No work scheduled Thursday December 24th – Friday January 1st
Lillian Dr.
- Rough grade for sod
Johns Pass Ave.
- Rough grade for sod
Flamingo Dr.
Crystal Dr.
- Replace Driveways – Concrete
Outfall Storm Pipes Install - Drainage Easements
- Irrigation restoration
Misc. Project wide
- Quality Control testing