Current Public Works Projects

Please see below for the current project going on throughout the City. If you have any questions or concerns please reach out to Megan Wepfer, Public Works Director.

Project Updates

Beach Groin Renourishment Project

  • Design is finalized and submitted for Permitting
  • Staff is working with FDEP and FWC for the construction schedule and will place the project to bid as soon as finalized.

Area 3 – E Parsley, W Parsley, Marguerite, A Street, B Street, and Lynn Way. Roadway and Drainage Improvement Project.

  • Submitted to FDOT for review. Public Works Department will be placing out to bid once finalized with FDOT

Area 5- 131st Ave E and 129th Ave Roadway and Drainage Improvement Project

  • Engineering Scope to be placed in March or Aprils Commission Agenda for approval to start design services.

Area 6a- Municipal Dr., Harbor Dr., 1st St. E., 2nd St. E., 153rd Ave., 154th Ave., & 155th Ave. Roadway and Drainage Improvements

  • Engineering Scope to be placed in March or Aprils Commission Agenda for approval to start design services.

Gulf Lane and Beach Access roadway and drainage improvements

  • The project will consist of Milling and resurfacing Gulf Lane along with 135th to 130th Beach access parking lots and improving the stormwater drainage.
  • Plans are complete and staff is working with Underground Consultant and Duke Energy to place the conduit in the ground for the future underground of all utilities.

Gulf Blvd Utility Undergrounding

  • Binding Cost Estimate is partially approved by the Board of Commissioners as of Feburary 13,2023,to start the boring of the conduit.
  • Task 2 – Construction management and Construction approved by the BOC September 14th.
  • Anticipated date for completion August 2023

FDOT Bridge Repair Project

Updates can be found at: 439565-1-52-01 SR 699/Gulf Blvd Bridge Maintenance over John's Pass (fdottampabay.com)

  • This project will provide routine maintenance to the lighting and moveable parts of the John's Pass bridges.
  • Construction is anticipated to begin in the spring of 2022 and be complete in the fall of 2023.

FDOT Gulf Blvd Water leak near 148th

  • FDOT has design plans to create an underdrain and connect it to their existing storm that runs down Gulf Blvd.
  • FDOT has no estimated start date as of January 24, 2023