Project Timeline and Updates
June 22 – July 10, 2020: All of Crystal Island
• Slow Down In Work Zones!
• No parking on streets project wide
• Keep children away from work areas
John’s Pass Ave. June 22-26
• Storm System – John’s Pass – 546/549 to 568/571
• Finish Base – 538/541 to south cul-de-sac
• 6″ WM Install Extend North – 577 to north cul-de-sac
Lillian Drive June 22-26
• Sub-Base and Base – 566/567 to Flamingo Dr
• Wet-Taps for Fire Hydrant Install
• Storm System – North end Tear Drop Park – Both Sides
Flamingo Drive June 22-26
• Seawall Southwest – Flamingo Dr (Betn Crystal & Lillian)
• Box Culvert Tie-In – 6×3 to Seawall
• Traffic Switch – One Lane Flamingo Dr for 7×4 Box Culvert Install (6/25)
Crystal Drive June June 22-26
• Wet-Taps for Fire Hydrant Install
John’s Pass Ave. June 29 – July 2
• Clean & TV Storm System
• Prime Finished Base – 538/541 to south cul-de-sac
• Prime Finished Base – 538/541 to south cul-de-sac
Lillian Drive June 29 – July 2
• Storm System – North end Tear Drop Park – Both Sides
• Sub-Base and Base North end of Tear Drop Park
Flamingo Drive June 29 – July 2
• Seawall Southeast – Flamingo Dr (Betn Lillian & Johns Pass) – Finish Seawall cap
• Seawall Southwest – Flamingo Dr (Betn Crystal & Lillian)
• Box Culvert Install – 7×4
Crystal Drive June 29 – July 2
• No work scheduled
Miscellaneous Project Wide
• Survey/Layout
• Quality Control Testing