Crystal Island Roadway / Drainage Schedule
Monday November 16th – Friday November 20th
Lillian Dr.
- Irrigation Restoration
- Copper water service lines replaced
Johns Pass Ave.
- Irrigation Restoration
- Restore Driveways
Flamingo Dr.
- Restore Driveways
- Reclaim water offset
- Pump Station Valve Replacement
Crystal Dr.
- Sub-Base and Base South of Flamingo Drive – Existing Base
- Prep for curb pad
- Machine Curb Install – 528/529 up to Flamingo Drive
- Reclaim water offset
- Watermain offset
Outfall Storm Pipes Install – Drainage Easements
- Storm Outfall Pipe – 498 Crystal Drive
- Storm Outfall Pipe – 496/498 John’s Pass
- Storm Outfall Pipe – 537/539 Lillian Dr
Misc. Project wide
- Quality Control testing
Monday November 23rd & Tuesday November 24th
No work scheduled Wednesday November 25th – Friday November 27th
Lillian Dr.
- Irrigation Restoration
Johns Pass Ave.
- Irrigation Restoration
- Restore Driveways
Flamingo Dr.
- Restore Driveways
Crystal Dr.
- Sub-Base and Base South of Flamingo Drive – Existing Base
- Prep for curb pad
- Water Main Offset work for Storm Conflict
- Machine Curb Install SB lane (extent of work will be listed on door hangers).
- Replace Driveways – Concrete
Outfall Storm Pipes Install – Drainage Easements
- Storm Outfall Pipe – 498 Crystal Drive
- Storm Outfall Pipe – 496/498 John’s Pass
- Storm Outfall Pipe – 537/539 Lillian Dr
Misc. Project wide
- Quality Control testing