Crystal Island Roadway / Drainage Schedule

Monday November 16th – Friday November 20th

Lillian Dr.

  • Irrigation Restoration
  • Copper water service lines replaced

Johns Pass Ave.

  • Irrigation Restoration
  • Restore Driveways

Flamingo Dr.

  • Restore Driveways
  • Reclaim water offset
  • Pump Station Valve Replacement

Crystal Dr.

  • Sub-Base and Base South of Flamingo Drive – Existing Base
  • Prep for curb pad
  • Machine Curb Install – 528/529 up to Flamingo Drive
  • Reclaim water offset
  • Watermain offset

Outfall Storm Pipes Install – Drainage Easements

  • Storm Outfall Pipe – 498 Crystal Drive
  • Storm Outfall Pipe – 496/498 John’s Pass
  • Storm Outfall Pipe – 537/539 Lillian Dr

Misc. Project wide

  • Quality Control testing

Monday November 23rd & Tuesday November 24th

No work scheduled Wednesday November 25th – Friday November 27th

Lillian Dr.

  • Irrigation Restoration

Johns Pass Ave.

  • Irrigation Restoration
  • Restore Driveways

Flamingo Dr.

  • Restore Driveways

Crystal Dr.

  • Sub-Base and Base South of Flamingo Drive – Existing Base
  • Prep for curb pad
  • Water Main Offset work for Storm Conflict
  • Machine Curb Install SB lane (extent of work will be listed on door hangers).
  • Replace Driveways – Concrete

Outfall Storm Pipes Install – Drainage Easements

  • Storm Outfall Pipe – 498 Crystal Drive
  • Storm Outfall Pipe – 496/498 John’s Pass
  • Storm Outfall Pipe – 537/539 Lillian Dr

Misc. Project wide

  • Quality Control testing