Please see below for an update on projects around the city. If you have any questions please feel free to give us a call 727-391-9951 or click here the current projects page.
John’s Pass Ave. Sept. 28- Oct. 2
- Storm Outfall Pipe – Easement 578/580 (weather permitting)
Crystal Drive Sept. 28- Oct. 2
- Storm Outfall Pipe – Easement 498 Crystal Dr (weather permitting)
Johns Pass Ave. Oct. 5 – 8
- Place Paver Driveways
Flamingo Dr. Oct. 5 – 8
- Install Curb
- Pump Station Valve Replacement
Crystal Dr. Oct. 5 – 8
- Sub-Base and Base North of Flamingo Drive
Outfall Storm Pipes Install Oct. 5 – 8
- Storm Outfall Pipe – John’s Pass Ave
- Storm Outfall Pipe – Crystal Drive
- Storm Outfall Pipe – Lillian Dr
- Seawall Penetrations of outfall pipes at seawalls
Misc. Project wide Oct. 5 – 8
- Survey/Layout
- Quality control Testing