The Building and Community Development Staff have been working tirelessly to get out Substantial Damage letters and push permits. Please see an update of permitting numbers since Sept. 27th.
ย
SUBSTANTIAL DAMAGE LETTERS:
๐ Total Determination Notifications Sent: 1369
PERMITS:
๐ Applications Processed 2539
๐ Permits Under Review: 205
๐ Permits Waiting to be reviewed: 46
๐ Permits waiting on more information from Applicant: 245
๐ Permits sent back to applicant due to missing information: 70
๐ Permits Issued: 2106