MADEIRA BEACH MASTER PLAN SURVEY

UPDATED ROADWORK SCHEDULE- Crystal Island

Posted on August 11, 2022


There will be NO STREET PARKING Friday, August 8th as well as Monday, August 15th to Friday, August 19th to milling and resurfacing of the roadways.

Due to some issues we will be placing new curbing at the following addresses:

574 to 566 Lillian Drive

Today we demoed the curb but left access to the residents driveway until Friday morning (8/12). Friday morning we will be removing the remainder of the curb and frame and pour new, Saturday, August 13th a crew will be out to remove the framing and allow access to those driveways. Paving is scheduled to start Monday, August 15th to Friday, August 19th. We will alert residence if the project is completed before August 19th.

 

Thank you for your patience as we fix the road issues. For any questions or concerns on the roadway project please reach out to the Public Works Department: 727-391-9951 x 401.

Crystal Island Roadway Project (2)