John’s Pass Ave. Sept. 28- Oct. 2

  • Storm Outfall Pipe – Easement 578/580 (weather permitting)

Crystal Drive Sept. 28- Oct. 2

  • Storm Outfall Pipe – Easement 498 Crystal Dr (weather permitting)

Johns Pass Ave. Oct. 5 – 8

  • Place Paver Driveways

Flamingo Dr. Oct. 5 – 8

  • Install Curb
  • Pump Station Valve Replacement

Crystal Dr. Oct. 5 – 8

  • Sub-Base and Base North of Flamingo Drive

Outfall Storm Pipes Install Oct. 5 – 8

  • Storm Outfall Pipe – John’s Pass Ave
  • Storm Outfall Pipe – Crystal Drive
  • Storm Outfall Pipe – Lillian Dr
  • Seawall Penetrations of outfall pipes at seawalls

Misc. Project wide Oct. 5 – 8

  • Survey/Layout
  • Quality control Testing